PI with Budget Control ​

Budget validation on Purchase Invoices works the same way as on Purchase Orders, with one important difference.

Budget Validation at Invoice Stage ​

When you submit a PI with a Budget Code (WBS), the system checks whether the available budget can cover the invoice amount.

Why Check Budget Again? ​

Budget was already checked when the PO was submitted. So why check again?

  • Time gap: Between PO submission and PI submission, other POs or invoices may have consumed the budget.
  • Amount differences: The invoice amount may differ from the PO amount (e.g., price changes, additional charges, partial delivery).
  • Direct invoices: If the PI was created without a PO, this is the only budget checkpoint.

Handling Budget Exceeded at Invoice Stage ​

If the PI submission is blocked due to insufficient budget, you have the same options as with PO:

  1. Request a Budget Amendment (increase)
  2. Request a Budget Transfer (move funds)
  3. Adjust the invoice amount
  4. Change the WBS code